“Policy can choose who goes first, but it cannot build the substation.”
Britain’s Data-Centre Queue: Who Connects First?

The prioritisation mechanism is confirmed. The framework for deciding what counts as ‘strategic’ is not published, and no ranking adds a megawatt of network.
On this page
Executive Summary
- On 28 October 2026 the government confirmed it will proceed with letting the National Energy System Operator (NESO) prioritise grid connections for strategic demand projects, data centres among them. The framework setting out the scope, criteria and process for choosing strategic projects, and the Covenant’s definition of a strategic data centre, are still to be published.
- The demand connection queue grew from 41 GW in November 2024 to 125 GW by June 2025, with about 73 GW of it from data-centre projects, according to the Office of Gas and Electricity Markets (Ofgem) July 2026 consultation. Ofgem fears the queue includes many speculative projects.
- Even prioritised projects will connect only as fast as the network can be built, the government says.
- The draft National Policy Statement (NPS) for data centres is out for consultation until 8 January 2027.
The Signal
The UK Department for Energy Security and Net Zero (DESNZ) published its response to the consultation "Accelerating electricity network connections for strategic demand" on 28 October 2026; the consultation opened on 11 March 2026.
The response confirmed that the government will proceed with two measures. NESO will prioritise strategic demand projects identified by government, using powers the government will exercise under the Planning and Infrastructure Act. Data-centre connections after 2030 will be aligned to regional infrastructure targets. The prioritisation measures are expected to be available before the next NESO connections application window; regional alignment will follow at a future window.
Both belong to the Demand Connections Reform programme and its three pillars. Curate, led by Ofgem, proposes a data-centre commitment fee and tougher progression milestones to filter out speculative applications; Ofgem’s decision is due in Q1 2027. Connect, also led by Ofgem, covers flexibility and connection choice. The government is leading Plan, which covers the prioritisation of strategic demand connections and the proposed regional alignment of data-centre connections.
The same day, HM Treasury published a Data Centre Covenant. It sets out five tests that strategic data centres must meet to qualify for extra government support, including faster grid connections and planning. The government will set up a Ministerial Control Centre, chaired by the Minister for AI, to consider support for strategic data centres. The government estimates the UK will need at least 6 GW of AI-capable data-centre capacity by 2030, which its draft NPS puts at around three times current capacity.
The Noise
The Covenant promises further details on the definition of strategic data centres “in due course”. On 3 November 2026, in a written answer to Parliament, minister Kanishka Narayan said the Department for Business, Innovation, Science and Trade “is developing a framework for assessing strategically important projects”, with further detail “in due course” (written question UIN 39193). No publication date was given.
The Covenant tests bind only the data centres that want extra government help; all data centres are encouraged to meet them. By our reading, meeting the tests does not by itself make a project strategic. Which projects ministers will designate as strategic — and on what evidence — is not yet public.
The draft National Policy Statement is the framework for deciding large data-centre projects in the Nationally Significant Infrastructure Project regime, not the route into it. It treats 100 MW of rated IT load as an indicative minimum for a section 35 direction into that regime. Its provisions are a draft, not yet designated policy.
Forensic Analysis
Silicon. The arithmetic of the queue.
By Ofgem’s count, about 73 GW of the demand queue is data-centre projects. Generation has already been through a version of this. NESO’s connections reform, whose results were published in December 2025, deprioritised up to 300 GW of excess battery and solar projects, according to DESNZ. Of the 217 GW that failed NESO’s strategic-alignment test, about 153 GW was batteries, 36 GW solar and 13 GW onshore wind; those projects were moved to Gate 1 offers rather than kept in line for a firm connection. The reform replaced first come, first served with a pipeline ordered by readiness and need.
Prioritising demand runs into the same arithmetic. Reallocated capacity comes only from projects that leave the queue or fall out of it, and a project with priority still cannot connect where there is no headroom. In 2022 parts of West London’s grid, home to many of its data centres, reached capacity, and the main reinforcement is not expected until 2037, according to a December 2025 London Assembly report.
Once the government has used its Planning and Infrastructure Act powers, NESO will be able to reserve and reallocate capacity for government-chosen projects, and the Covenant says the government will use the same powers, where needed, to facilitate the transfer of pre-2030 data-centre connection contracts to strategically important data centres. None of this creates physical network capacity that does not exist.
Stone. The governance gap.
The government will publish the projects it considers strategic and direct NESO on how to prioritise them. In our reading, that is a significant step beyond a queue ordered only by readiness and strategic fit.
What is missing is the published framework for choosing strategic projects. The regional infrastructure targets that will govern data-centre connections after 2030 are not yet defined; the Covenant says the alignment will be informed by the ALIGN spatial planning tool. Temporary on-site generation, to bridge the gap until a grid connection can be secured, will be reserved for “exceptionally strategic” projects, and only where other measures cannot secure capacity in time, under a framework the government has yet to develop.
Strategic Implication
Until the government publishes its framework for choosing strategic projects, and no date has been given, a connection timeline that depends on prioritisation cannot be underwritten with confidence. Model two cases: the project is designated, and it is not. Price the second as the base case.
The next fixed date is the close of the draft NPS consultation on 8 January 2027. Anyone with views on how large projects should be decided should respond by then. Ofgem’s Curate decision is due in Q1 2027; that is when the commitment fee and milestones move from proposal to decision.
For anyone siting capacity beyond 2030, treat location as a live variable: connections will be aligned to regional targets that do not yet exist.
The Long View
Britain has the outline of a coherent policy architecture for a queue that stopped working, and the Ministerial Control Centre will give government a direct lever over who connects first.
The gap is definitional. “Strategic” is the word on which large investment decisions will turn. Narayan’s answer offered a description — strategically important data centres “will be the projects that offer the greatest value to the UK” — and the framework for assessing it is not yet published.
Watch for
- Publication of the framework for choosing strategic projects, and the Covenant’s definition of a strategic data centre (no date given).
- The close of the draft NPS consultation on 8 January 2027, and the government’s response after it.
- Whether the prioritisation measures arrive before the next NESO connections application window, as expected.
About 73 gigawatts of data-centre projects are chasing a network that in West London ran out of room in 2022: policy can choose who goes first, but it cannot build the substation.
- Supply Chain × Scenario Modelling
- Supply Chain × Long-Memory Filter
- Policy × Scenario Modelling
- Policy × Long-Memory Filter
- Talent × Scenario Modelling
- Talent × Long-Memory Filter
2 of 6 cells applied
Sources
- Gridlocked: how planning can ease London's electricity constraints — London Assembly Planning and Regeneration Committee
- Draft National Policy Statement for Data Centres — Department for Business, Innovation, Science and Trade
- Data Centres: Terminology — Written Answer UIN 39193 — UK Parliament
- Draft National Policy Statement for Data Centres — Department for Business, Innovation, Science and Trade, GOV.UK
- The Data Centre Covenant — HM Treasury / GOV.UK
Clive Struver
Founder & Editor
Clive Struver is the founder and editor of Silicon and Stone. Across forty years in the technology industry he led European and EMEA operations for Motorola, Anritsu, Giant International and WDS Global — running semiconductor, test, and electronics businesses through repeated industry cycles — before moving into independent advisory and team-turnaround work. He writes Forensic Technopolitics from an island in Orkney, sixty miles north of the Scottish mainland, bringing an operator's eye to AI regulation, semiconductor supply chains, and digital sovereignty. A career spanning Europe, the US and Asia.
More from Clive Struver →Relevant for:
Policy Intelligence
Quantify the Atlantic Drift. Regulatory divergence analysis for strategic planning.
No spam. Unsubscribe anytime.
Related Intelligence
EU AI Act: What 2 August 2026 Actually Requires (and What Moves to 2027–28)
2 August 2026 moves the transparency line and switches on the penalty regime; the heavy high-risk obligations move to December 2027 and August 2028.
Iran Conflict: How a Middle Eastern War Becomes a European Technology Supply Crisis
Iran's conflict is squeezing rare earth flows, specialty chemicals, and MLCC supply.
Brussels Has Five Tools to Fight Washington's Tech Aggression — Only One Is a Rulebook
The EU's response to US tech coercion spans five instruments — regulation is the weakest. CAIDA's structural contradiction and the interim dependency window